Tag Archives: Requirement Group

Variations of the Requirement Group setup and further detailed hints

Requirement Groups – options for alternative combinations

When creating a Requirement Group or a Requirement Group Template we are able to configure several possible combinations of Group members within one Requirement Group.

Example: We have a large Implementation Project and need two Project Managers. But these could either be one Senior plus one Junior, or alternatively two Project Managers on the Advanced level.

Our Resources are set up with these Skills and Rating Values:

Our Requirement Group (Template) will look like this:

Additionally I have opened each of the four Requirements of this Group configuration and set the corresponding Rating Value:

When we than execute the search by hitting the Book button in the ribbon of the Requirement Group (Template), and raising the Results Per Interval to 10, we’re getting these results:

Recognize that we are getting all possible combinations of Resources to fulfill each of the Requirements with an appropriate skill level in the configured combination and the system also respects our Rating Value. For example it does not propose to create a Group of Tom and Tim because Tom has only a low skill level (familiar) that would require a Senior (proficient skill level) on his side according to our configuration.

Requirement Group functionality

  • you can’t schedule Requirements that are part of a Requirement Group by using the Schedule Board. Use the Book-button from the parent record instead.
  • Requirement Groups are possible for Onsite, Location Agnostic and Facility Work Locations.
  • Always the same for all Requirements of a Requirement Group (updating them on one Requirement updates them on all others from the same Group automatically):
    • Duration (also gets auto-populated/updated from ‘Work Order’.’Primary Incident Estimated Duration’)
    • Fulfillment Preference
    • Work Location (also gets auto-populated/updated from Work Order changes)
    • Latitude/Logitude (also gets auto-populated/updated from Work Order changes)
    • From Date / To Date (also gets auto-populated/updated from ‘Work Order’.’Date Window Start’ /’Date Window End’).
    • Booking Setup Metadata and schedulable entity (Work Order, Project, custom entity, …)

Sources and more information:
https://docs.microsoft.com/en-us/dynamics365/customer-engagement/field-service/multi-resource-scheduling-requirement-groups

Hints for working with Requirement Groups in Work Orders (by leveraging Incident Type Requirement Groups)

Preferred Resources

If a Primary Incident Type that contains an Incident Type Requirement Group has been used in a Work Order, than the Resource Preferences which are kept as child records of the Service Account are not auto-populated neither into the Work Order nor into the Requirement Group based Resource Requirements of this Work Order.

However we can associate Preferred Resources to the Requirement Group Template.

Here a Requirement Group Template without preferred Resources:


Leading to these search results when setting the Results Per Interval to 3:

But if we now add two defined Resources into the Preferred Resource field of our “Associate”-Requirement of the Requirement GroupTemplate:

and than perform the search again with the setting of 3 Results Per Interval, we’re only getting two results per interval back:

This is because we have restricted the number of possible Resources for one of the Requirements to two. And because we don’t have any other Resources available which could fulfill the “Technician”-Requirement, there are only two options left per interval.

So if you have large customers who each have a certain selection of possible Resources (similar to Resource Preferences under the Account record), than you could create one Incident Type per large customer that, in combination with one Requirement Group Template per large customer, serve as a replacement of the Preferred Resource (Resouce Preferences with Preference Type: Preferred) under the Account.

Technically the entity Requirement Resource Preference serves as a container for Preferred Resources under
a) the Account
b) the Resource Requirement of a Work Order
c) the Resource Requirement of a Requirement Group Template

Find more info here: Requirement Resource Preference

Share it on

Requirement Groups in Work Orders

In a former article I have explained how Requirement Groups and Requirement Group Templates work.

Now I’m going to show you how these can be leveraged when using Work Orders.

Configure the Incident Type

  1. create a Requirement Group Template as explained in above mentioned article
  2. create a new Incident Type: Field Service=>Settings=>Incident Types=>”+ New”
  3. Give the new Incident Type a name (my recommendation: provide a hint in the name that helps you later on to remember that this Incident Type is based on a Requirement Group):

4. On the Incident Type form, go to Related=>Requirement Groups
5. create a new Incident Type Requirement Group:

6. associate the formerly created Requirement Group Template to it via the lookup field
7. provide a name to the record and save it.

So you should finally get something like this:

Test it with a Work Order

Now its up to you to test the whole setup.
For doing this you just need to create a new Work Order and fill in our new Incident Type into the field Primary Incident Type on the Work Order form:

Note: With a standard Field Service setup you necessarily need to provide the group based Incident Type in the field Primary Incident Type BEFORE you save the Work Order the first time. Otherwise you’ll get an error saying “You can’t add an incident that is related to a requirement group template to a work order if there is already a requirement related to this work order.”

Than you can check if your Requirements have correctly been associated with the Work Order. For doing so you need to go to: Related=>Requirements=> change the View to “Unsubmitted“:

Customized Work Order form and Requirements view

Customization recommendation (especially if you more often have group based Requirements): create your own Resource Requirement view for the Work Order form.

And now the big moment comes: hit the Book button on top of the Work Order form:

You should now get search results according to the available Resources, the distance to the Service Location and the other parameters like Work Location, Organizational Unit, Resource Type and so forth:

Note: if you are going to use the same or a similar combination of Resources more often, it makes sense to create Requirement Group Templates whereas if you need a certain combination of Resources/Skills only one time it would theoretically be enough to create a Requirement Group without a Template. However it seems like if go down that road, you will not be able to associate your Requirement Group to a Work Order anymore later on. At least I couldn’t find a way to do that. That means that if you want your Users to be able to click the Book button on a Work Order and have the fancy algorithm execute its sophisticated multi-resource query, you will always need to create an Incident Type for it first and associate a Requirement Group Template to it.

What you can do is going back from a created Work Order that has a Requirement Group associated via =>Resource Requirement=>Requirement Group (or simply from the Field Service menu: Requirement Groups) and there editing the instance of the Requirement Group that is responsible for your Work Order.
This method allows you to create a kind of a standard Incident Type Requirement Group and Template which you always use for creating a new Work Order when you want to leverage the Group functionality.

Cascading & sync of attributes within the Requirement Group

a) Cascading attribute changes from Work Order to Requirements

(as of Sept. 2019)

gets initially populated and auto-updated for the Resource Requirement with flag “Is Primary“ only:

  • Time From Promised/Time To Promised
  • Time Window Start/Time Window End
  • Service Territory (remove)

gets initially populated and auto-updated for all associated Resource Requirements:

  • Duration
  • Date Window Start/Date Window Start End (into fields From Date / To Date )
  • Latitude/Longitude
  • Work Location
  • Service Territory (Create, Change)

b) Attributes kept in sync between Resource Requirements

Duration, From/To Date, <long/Lat, Work Location are always kept in sync within the Requirement Group, even when changed on a non-primary Requirement.

Service Territory however is only kept in sync, when it was changed from the Work Order AND the change was not a removal of the field content. So you can open the non-primary Requirements and assign different Territories to each.

As an example you might end up having Requirements like this in the end:

– Time Promised From/To and Time Window Start/End is only populated to the primary Requirement
– Territory has been removed from the Work Order after initial creation: this removal is cascading only to the primary Requirement (whereas an UPDATE/CREATE of the Territory would have been cascaded to all Requirements)

When asking yourself why is there a difference of cascading between Time Promised/Time Window vs. Date Window you can come to the assumption that it has to do with the Requirement Group functionality. If we check the UI (screen below) we can easily see that there are only the From Date / To Date fields (which are the counterparts to Date Window From /To from the Work Order). So Microsoft only takes care for a synchronization of these fields within a Requirement Group but not for the other Date/Time fields.

I was asking myself how can you have differing values in the Time Promised fields for Requirements of the same Requirement Group? As soon as you are scheduling or re-scheduling them, all of the Bookings based on these Requirements get moved simultaneously.
However it could make sense if you have a scenario where a team gets a Booking for a longer period of time (i.e. traveling on site together) but the actual “ToDo” of a Resource would only be for a shorter time frame and you want to keep this information somewhere.
If you are going to use it this way you should surely not create a hard booking restriction – for example with a Real Time Workflow – which forces you to not book outside of time promised from/to.

Also note that a Time From/To Promised on one of the non-primary Requirements will be ignored completely by the Schedule Assistant. However a Time From/To Promised on the Primary Requirement is a hard selection criteria for the Schedule Assistant, even if it doesn’t show these fields in the Filter panel, when scheduling a Requirement Group [improve@MS].

Find in my next article variations of the Requirement Group setup and further detailed hints related to it.

Share it on

Requirement Group

After we have taken a look into Resource Crews let’s now explore what Dynamics 365 Customer Engagement can offer with Requirement Groups.

  1. create three Resources, each with differing skills:
    Go to Field Service=>Resources=>”+ New” and create
    a) One User with Skills: Flow, Hololens Know How.
    b) One Contact with Skill: Data Integration
    c) One Equipment with Skill: Hydraulic Lift

2. create a Requirement Group Template. Go to Field Service=>Resources=>Requirement Group Templates=>”+ New”
a) provide a Name, save
b) click into the first row from the subgrid and click “+ Requirement
c) now add three requirements for getting back proposals for a team of three people and add corresponding skills
d) at the Truck Resource click on Open Form to determine which Resource Type (Equipment in this case) you are expecting

Difference between Requirement Group and Requirement Group Template

A bit confusing is, that as soon as you open a Requirement Group Template form, the menu on the left jumps back as if you would have opened a Requirement Group instead of a Requirement Group Template. [improve@MS]
Reason: technically Requirement Group and Requirement Group Template are the same entity msdyn_requirementgroup where only the records are differentiated by a flag called “Is Template”.

The title of the new-form “New Template: …” gives you the indicator that you’re creating a new template. But if you’re going to edit an existing Requirement Group Template you feel like editing a Requirement Group instead. I would therefore recommend to make the flag “Is Template” visible but read-only on the form.

If you pay close attention you recognize another difference: the lookup field Requirement Group Template is only visible on the Requirement Group form:

The field Requirement Group Template is read only for saved records.

That brings us to the interoperability of the two:
if you create a new Requirement Group the above mentioned field gets unlocked so you can choose a Requirement Group Template to start from.

Book a Requirement Group

If done with editing the requirements you can click the Book button directly from the Requirement Group ribbon:

This will open the Schedule Assistant with a list of appropriate Resource combinations. In our example the three Resources we have configured in step 1:

On the result list you than can

  • open each result row’s group to see its members
  • see which of the Requirements are going to be fulfilled by which of the found resources (last column)
  • adjust filter criteria and repeat search execution
  • book one of the groups by clicking on it => Book & Exit on the right flyout

If you’re not getting any results you should

  • probably need to adjust your search criteria
  • check if you have appropriate Resources in the system at all
  • check whether your Requirements do have a Service Territory associated but your Resources haven’t

Requirement Group in Schedule Board

If you now open the Schedule Board you could find something like this (too many Resources to have an easy overview):

Hovering over the booking panel (screenshot above) tells you that you have a Grouped Booking. So maybe you want to do a right click at the booking and choose Split View:

Shows you all bookings from this group (only those Resources which are on the same page of results, so you might want to increase the number of Resources per Page in Schedule Board tab settings and/or adjust your Resource filter to see all group members).

If you now drag and drop one of the bookings to a different starting time, all other bookings of this group will be shifted automatically too. Cool! That is what our customer wants!
However compared to the same procedure with a Resource Crew you don’t see the shifting immediately happening on the board, instead you need to hit the refresh-button at the top of the Schedule Board tab once to see your bookings being shifted [improve@MS].

In another article I’m going to dig deeper into the combination of Requirement Groups with Work Orders.